Stones on walls were marked for guide when they are reinstalled (NPS photos) |
Extensive
work on the famous Burnside Bridge at Antietam National Battlefield in Maryland
is nearing the one-year mark, and officials expect it to continue until the end
of the year.
The $1.7
million preservation project is bringing repairs and stabilization to the stone
structure, which was built in 1836.
Park Superintendent
Susan Trail responded Friday to the Picket’s questions about the bridge project. She said the project is going “very well.”
Temporary dams were built for work on eroded pier bases. |
Q. You said the piers would be repointed and the
voids filled with grouts. Has that been completed? Was that the extent of the
work on the piers?
A. All of
the pier work was completed in late winter. The work was extensive, as concrete
ribbon footers had to be poured for each due to extensive erosion.
Q. I saw some Facebook
photos (above) last week of work on top of the bridge. What's that work? Looks like
maybe some wall reconstruction and a new walking surface?
A. Most of the work on the
stone bridge involved dismantling substantial sections and rebuilding them.
This is the work that is going on right now. The wall sections were
photographed and mapped, so that the stones could be returned to their exact
locations prior to the dismantling. The repaving will happen later this fall
when the stone work is complete.
Q. Can you briefly
summarize what all has been addressed in this restoration/preservation effort?
A. The project addressed
substantial voids and erosion in the two piers and the two abutments. It also
addressed unstable parapet and spandrel walls that had deteriorated over the
years, due primarily to water infiltration. It also will include new wood
coping and asphalt paving, which will be done this fall.
East bridge abutment |
Q. What do you hope will
be the long-term benefit of the work?
A. This
project will keep the bridge standing in good condition for decades to come.
Q. Anything unexpected
come up during the construction/repairs?
A. The
biggest unforeseen condition was the severe erosion of the pier bases, as this
could not be seen before the project started.
On Sept. 17, 1862, America's
bloodiest single day, a small force of Confederates on high ground for
three hours defended the critical crossing against troops belonging to Ambrose
E. Burnside's 9th Corps.
Portion of bridge that bulged, needed repairs |
Critics say Burnside did not do adequate reconnaissance before the
attack, which cost him about 500 casualties.
"After taking the bridge at about 1 p.m., Burnside reorganized for two hours before moving forward across the arduous terrain -- a critical delay. Finally, the advance started -- only to be turned back by Confederate General A.P. Hill’s reinforcements that arrived in the late afternoon from Harpers Ferry," according to the NPS.
"After taking the bridge at about 1 p.m., Burnside reorganized for two hours before moving forward across the arduous terrain -- a critical delay. Finally, the advance started -- only to be turned back by Confederate General A.P. Hill’s reinforcements that arrived in the late afternoon from Harpers Ferry," according to the NPS.
After the battle, the bridge was actively used for traffic until as
recently as 1966, according to the NPS. The last significant work occurred in the late 1980s.
No comments:
Post a Comment